Update for NHHS Measure A Project

Robins Hall Remodel
Loats Theater

Updated Progress (10/4/04):
Newport Harbor’s Measure A modernization began this summer with the installation of a new electrical distribution system. Doing this project during the summer insured that no trenches will have to be dug through the campus during the school year. Contractors were also able to replace the plumbing infrastructure and to lay conduit to accommodate future telecommunication needs.

This week work began in Beek Hall. Carpets have already been removed. Tiles are being removed now under strict asbestos containment procedures which are monitored by a state-approved inspector. Our contractor, the Mackone Company, will be providing me with a more detailed construction schedule in the next ten days.